SISHEN O&M AUDIT AND SURVEILLANCE – 10/2021

 

GENERAL PROJECT INFORMATION

Location: Dibeng, Northern Cape (South Africa).

Peak capacity: 94.3 MWp.

Nominal capacity: 74 MW.

Technology: Photovoltaic solar with horizontal tracking. Start-up: 2014.

Client: ACCIONA

Acciona Certificate.png
Picture6.png

MET MAST INSTALLATION INSPECTION AND VERIFICATION – 2021 -2022

The Excelsior Wind Energy Facility is a 32.5MW - Swellendam, WC.

The Garob Wind Power Station is a 145MW – Copperton, NC.

Golden Valley Wind Power Project is a 120MW - Eastern Cape, South Africa.

Client: UL Solutions

We have also worked in Kleinsee, Gouda, Loeriesfontein and Poffadder across South Africa and Ghana.